# Customer Plant Year Duration Scope Size/Category Qty Remarks
1 ARAMCO ABGOSP 3 Dec-13 10 days (Day/night shift) Cold Cuts Welding Plug Tests Manpower Supply 10 inch 8 inch 8 inch 10 inch 10 x 150 6 x 150 4 x 150 Metalman Welders Fabricator 4 16 2 2 6 2 1 30 6 6 complete
2 ARAMCO SHD-6 Dec-13 6 days (Day/night shift) Plug Tests Plug Tests Welding Manpower Supply 8 inch 16 inch 6 inch 10 inch 8 inch 16 inch 8 inch 16 inch Metalman Welders Fabricator 6 4 3 4 1 1 2 2 20 3 3 complete
3 ARAMCO ADGOSP 2 Jan-14 6 days (Day shift) Flange Spreading 42 inch 48 inch 2 2 complete
4 ARAMCO ABGOSP 3 Jan-14 15 days (Day Shift) Nozzle Replacement for Sand Trap 12 inch 14 inch 24 inch 24 12 6 complete
5 ARAMCO AINDAR-2 Feb-14 15 days (Day Shift) Cold Cuts Torquing Flange Fixing Flange Fixing Manpower supply 24 inch 30 inch 16 inch 12 inch 16 inch 20 inch 3 inch 30 inch 12 inch 3 inch 30 inch 12 inch 24 inch 3 inch Metalman Welders Fabricator 19 1 1 2 23 1 2 1 2 2 1 2 1 2 60 10 8 complete
6 ARAMCO AINDAR-1 Feb-14 15 days (Day Shift) Torquing Welding Plug Test Manpower supply 24 inch 36 inch 20 inch 16 inch 12 inch 20 inch 20 inch 16 inch 12 inch Metalman Welders Fabricator 4 2 6 1 1 8 2 1 1 60 10 8 complete
7 ARAMCO NGID Mar-14 30 days (Day/Night Shift) Manpower supply Metalman Welders Fabricator Pipe Fitter Crew Cab 18 6 6 10 4 complete
8 ARAMCO SHD-2 & 5 Mar-14 30 days (Day/Night Shift) Cold Cuts Torquing Flange Fixing Flange Fixing Manpower supply 24 inch 30 inch 16 inch 12 inch 16 inch 20 inch 3 inch 30 inch 12 inch 3 inch 30 inch 12 inch 24 inch 3 inch Metalman Welders Fabricator 22 1 2 4 23 1 2 2 2 4 1 4 1 2 40 12 10 complete
9 ARAMCO ABGOSP 2 Apr-14 15 days (Day Shift) Nozzle Replacement for Sand Trap 12 inch 24 inch 2 2 complete